Project Highlights
|
 |
GE Healthcare - Diagnostic Imaging
PM have been project managers, engineers and construction managers for all of GE Healthcare (formerly Amersham Health) developments in Cork, Ireland since the early 1990's.
The 10,500m² facility has clean room classifications ranging from Grade A to D. To date the following projects have been completed:
Phase 1 Development 1991-1993: Refurbishment of an existing production facility to incorporate the full range of process, utility and support operations
Phase 2 Expansion 1995-1996: Additional process areas and a new warehouse
Product Transfer 1997-1998: Additional glass filling line and Blow Fill Seal machine
Global Sourcing 1999-2002: Additional production capacity, a new filling line and a new packaging building
Strategic Site Master Plan: 2001 A roadmap for future investments in Cork up to 2011.
Filling Line 4 2002-2003: Additional filling line and additional utilities infrastructure
At Amersham Health's Shanghai plant, PM carried out a Front-end study for the introduction of additional products, and later developed a Site Master Plan. Meanwhile at Amersham Health's bulk production plant in Lindesnes Norway, PM assisted with a pre-engineering study into potential production changes in the plants.
|