PM have been project managers, engineers and construction managers for all of GE Healthcare (formerly Amersham Health) developments in Cork, Ireland since the early 1990's.
GE Healthcare
The 10,500sqm facility has clean room classifications ranging from Grade A to D. To date the following projects have been completed:
Phase 1 Development 1991-1993: Refurbishment of an existing production facility to incorporate the full range of process, utility and support operations
Phase 2 Expansion 1995-1996: Additional process areas and a new warehouse
Product Transfer 1997-1998: Additional glass filling line and Blow Fill Seal machine
Global Sourcing 1999-2002: Additional production capacity, a new filling line and a new packaging building
Strategic Site Master Plan: 2001 A roadmap for future investments in Cork up to 2011.
Filling Line 4 2002-2003: Additional filling line and additional utilities infrastructure
At Amersham Health's Shanghai plant, PM carried out a Front-end study for the introduction of additional products, and later developed a Site Master Plan. Meanwhile at Amersham Health's bulk production plant in Lindesnes Norway, PM assisted with a pre-engineering study into potential production changes in the plants.